We are looking forward to your testimony before the Subcommittee on Oversight and Investigations on Thursday, June 17,2010, about the causes of the blowout ofthe Macondo well and the ongoing oil spill disaster in the Gulf of Mexico. As you prepare for this testimony, we want to share with you some of the results of the Committee’s investigation and advise you of issues you should be prepared to address.
The Committee’s investigation is raising serious questions about the decisions made by BP in the days and hours before the explosion on the Deepwater Horizon. On April 15, five days before the explosion, BP’s drilling engineer called Macondo a “nightmare well.” In spite of the well’s difficulties, BP appears to have made multiple decisions for economic reasons that increased the danger of a catastrophic well failure. In several instances, these decisions appear to violate industry guidelines and were made despite warnings from BP’s own personnel and its contractors. In effect, it appears that BP repeatedly chose risky procedures in order to reduce costs and save time and made minimal efforts to contain the added risk.
At the time of the blowout, the Macondo well was significantly behind schedule. This appears to have created pressure to take shortcuts to speed finishing the well. In particular, the Committee is focusing on five crucial decisions made by BP: (I) the decision to use a well design with few barriers to gas flow; (2) the failure to use a sufficient number of “centralizers” to prevent channeling during the cement process; (3) the failure to run a cement bond log to evaluate the effectiveness of the cement job; (4) the failure to circulate potentially gas-bearing drilling muds out of the well; and (5) the failure to secure the wellhead with a lockdown sleeve before allowing pressure on the seal from below. The common feature of these five decisions is that they posed a trade-off between cost and well safety.
Well Design. On April 19, one day before the blowout, BP installed the final section of steel tubing in the well. BP had a choice of two primary options: it could lower a full string of “casing” from the top of the wellhead to the bottom of the well, or it could hang a “liner” from the lower end of the casing already in the well and install a “tieback” on top of the liner. The liner-tieback option would have taken extra time and was more expensive, but it would have been safer because it provided more barriers to the flow of gas up the annular space surrounding these steel tubes. A BP plan review prepared in mid-April reconunended against the full string of casing because it would create “an open annulus to the wellhead” and make the seal assembly at the wellhead the “only barrier” to gas flow if the cement job failed. Despite this and other warnings, BP chose the more risky casing option, apparently because the liner option would have cost $7 to $10 million more and taken longer.
Centralizers. When the final string of casing was installed, one key challenge was making sure the casing ran down the center of the well bore. As the American Petroleum Institute’s recommended practices explain, if the casing is not centered, “it is difficult, ifnot impossible, to displace mud effectively from the narrow side of the annulus,” resulting in a faiku cement job. Halliburton, the contractor hired by BP to cement the well, warned BP that the well could have a “SEVERE gas flow problem” if BP lowered the final string of casing with only six centralizers instead of the 21 recommended by Halliburton. BP rejected Halliburton’s advice to use additional centralizers. In an e-mail on April 16, a BP official involved in the decision explained: “it will take 10 hours to install them . … I do not like this.” Later that day, another official recognized the risks of proceeding with insufficient centralizers but commented: “who cares, it’s done, end of story, will probably be fine.”
Cement Bond Log. BP’s mid-April plan review predicted cement failure, stating “Cement simulations indicate it is unlikely to be a successful cement job due to formation breakdown.” Despite this warning and Halliburton’s prediction of severe gas flow problems, BP did not run a 9- to 12-hour procedure called a cement bond log to assess the integrity of the cement seal. BP had a crew from Schlumberger on the rig on the morning of April 20 for the purpose of rUlUling a cement bond log, but they departed after BP told them their services were not needed. An independent expel1 consulted by the Committee called this decision “horribly negligent.”
Mud Circulation. In exploratory operations like the Macondo well, wells are generally filled with weighted mud during the drilling process. The American Petroleum Institute (API) recommends that oil companies fully circulate the drilling mud in the well from the bottom to the top before commencing the cementing process. Circulating the mud in the Macondo well could have taken as long as 12 hours, but it would have allowed workers on the rig to test the mud for gas influxes, to safely remove any pockets of gas, and to eliminate debris and condition the mud so as to prevent contamination of the cement. BP decided to forego this safety step and conduct only a partial circulation of the drilling mud before the cement job.
Lockdown Sleeve. Because BP elected to use just a single string of casing, the Macondo well had just two barriers to gas flow up the annular space around the final string of casing: the cement at the bottom of the well and the seal at the wellhead on the sea floor. The decision to use insufficient centralizers created a significant risk that the cement job would channel and fail, while the decision not to run a cement bond log denied BP the opportunity to assess the status of the cement job. These decisions would appear to make it crucial to ensure the integrity of the seal assembly that was the remaining barrier against an influx of hydrocarbons. Yet, BP did not deploy the casing hanger lockdown sleeve that would have prevented the seal from being blown out from below.
These five questionable decisions by BP are described in more detail below. We ask that you come prepared on Thursday to address the concerns that these decisions raise about BP’s actions.
The Committee’s investigation into the causes of the blowout and explosion on the Deepwater Horizon rig is continuing. As our investigation proceeds, our understanding of what happened and the mistakes that were made will undoubtedly evolve and change. At this point in the investigation, however, the evidence before the Committee calls into question multiple decisions made by BP. Time after time, it appears that BP made decisions that increased the risk of a blowout to save the company time or expense. If this is what happened, BP’s carelessness and complacency have inflicted a heavy toll on the Gulf, its inhabitants, and the workers on the rig.
During your testimony before the Committee, you will be asked about the issues raised in this letter. This will provide you an opportunity to respond to these concerns and clarify the record. We appreciate your willingness to appear and your cooperation in the Committee’s investigation.
Sincerely,
Henry A. Waxman, Chairman, Committee on Energy and Commerce
Bart Stupak, Chairman, Subcommittee on Oversight and Investigations
Copyright 2023 Nexstar Media Inc. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed.